Topic: 请教个问题,为什么计划订单不能转生产订单?

ERP俱乐部

第 1 页 总共 1 页 [共有 7 条记录]


Posted by luodany on 2007-06-08 09:04 上午
各位大虾 ,请教个问题,为什么计划订单不能转生产订单?
计划订单0000036839/INDR,INDR表示什么意思?

Posted by luodany on 2007-06-08 09:06 上午
计划策略是40 的策略

Posted by arica on 2007-06-08 11:07 上午
呵呵,写详细点,你是怎么操作的,有什么提示信息等呀

Posted by luodany on 2007-06-08 12:29 下午
先用MD61输入计划独立需求,然后运行MRP ,用MD04察看,有计划订单0000036839/INDR,但这个计划订单不让转生产订单

Posted by 開心 on 2007-06-08 06:12 下午
Conversion indicator for planned order
This indicator specifies whether the planned order can be converted into a production order or a process order, or into a purchase requisition.

Note
If the system finds a valid BOM for the planned order and if the release of the BOM for the planned order has been activated in the BOM status, the system automatically sets the conversion indicator in the planned order. If you have not activated the release of the BOM for the planned order, the system does not set the conversion indicator.

If the system cannot find a valid BOM, the coversion indicator is then also set, as production orders without BOMs, that is, without components, can also be created.

You can also set the conversion indicator yourself, independent of the BOM status, in the planned order

Posted by 寻梦客 on 2007-06-15 04:08 下午
你的strategy是不是选择为50,或者是因为上层的strategy跟下层的strategy冲突,所以不能转成生产订单,检查一下planned order的type,这个应该是"VP".

Posted by william0307 on 2007-06-18 09:43 下午
没有详细得错误或者提示信息吗?